Broadlands Dam
The Broadlands Dam (also known as the Broadlands Hydropower Project by the developers) is a 35 MW run-of-the-river hydroelectric complex currently under construction in Kitulgala, Sri Lanka. The project is expected to be completed in 2020, and will consist of two dams, and a power station further downstream.
Wikipage disambiguates
Wikipage redirect
primaryTopic
Broadlands Dam
The Broadlands Dam (also known as the Broadlands Hydropower Project by the developers) is a 35 MW run-of-the-river hydroelectric complex currently under construction in Kitulgala, Sri Lanka. The project is expected to be completed in 2020, and will consist of two dams, and a power station further downstream.
length (km)
has abstract
The Broadlands Dam (also known ...... Equipment Corporation (CNEEC).
@en
building start year
country
description
G
@en
vastest lake
length (μ)
location
opening year
part
river
Link from a Wikipage to an external page
Wikipage page ID
40,687,961
page length (characters) of wiki page
Wikipage revision ID
1,003,365,204
Link from a Wikipage to another Wikipage
construction began
2013-07-17
cost
country
dam crosses
dam type
G
@en
image size
Location
name
Broadlands Dam
@en
opening
plant annual gen
plant capacity
plant operator
plant turbines
purpose
P
@en
status
UC
@en
website
wikiPageUsesTemplate
subject
point
6.978888888888889 80.45444444444445
comment
The Broadlands Dam (also known ...... er station further downstream.
@en
label
Broadlands Dam
@en
sameAs
lat
6.978888888888889e+0
long
8.045444444444446e+1
wasDerivedFrom
homepage
isPrimaryTopicOf
name
Broadlands Dam
@en